Top Story
Digit@l FurnaceŽ of BlueScope Steel in Autralia - First hot slabDischarging of the first slab from this new 100 % Digit@l furnaceŽ on 11 July 2006 was the result of over three years of individual and collective efforts of several companies including STEIN HEURTEY as the main supplier.
The design work for this 415 t/hr furnace started after contract signing in August 2004. Though the civil work was completed by the customer 6 months behind schedule which delayed start of the furnace construction by at least 3 months, the production could begin on schedule thanks to the drastic programme implemented to make up for lost time. BLUESCOPE STEEL´s satisfaction on this performance has been clearly expressed. After nearly 4 months of production the record values achieved have confirmed the first objective of Bluescope Steel which was to increase the yearly production by 400,000 tonnes. It has also been a success in terms of quality since the slabs rolled since 11 July 2006 have met the requirements for their marketing.
08.08.2006, Stein Heurtey News material on the Site is copyright and belongs to the Company or to its third party news provider, and all rights are reserved. Any User who accesses such material may do so only for its own personal use, and the use of such material is at the sole risk of the User. Redistribution or other commercial exploitation of such news material is expressly prohibited. Where such news material is provided by a third party, each User agrees to observe and be bound by the specific terms of use applying to such news material. We do not represent or endorse the accuracy or reliability of any of the info contained in any news or external websites referred to in the news.
|
Search News
INFO
Category
News by language
Company Profile
NEWSLETTER
Services
|
Advertisement
|